Concrete pavement is strong in the panel and vulnerable at the joint.
Why concrete lots have joints at all
Concrete shrinks as it cures and moves with temperature for its whole life. Joints are planned breaks that control where cracking happens and let panels move. A commercial lot or truck court is a grid of panels separated by contraction joints, plus isolation joints at buildings, drains and other fixed objects.
How water does the damage
An open joint channels runoff to the base under the slab. With every heavy wheel load the panel edges deflect slightly and pump water and fine base material out through the joint. Over time a void forms under the panel edge. The unsupported concrete then cracks, usually at the corners and along the wheel path. In North Texas, expansive clay subgrades add another source of movement when they get wet.
Open joints also collect sand and stones. When the panels expand in summer they bear on that debris, and the joint edges spall.
What a correct sealing job includes
Sealant only works as well as the joint it's installed in. A durable job includes:
- Removing old sealant and debris completely, by routing or sawing.
- Cleaning the faces with pressure and air so they're clean and dry.
- Repairing spalled edges so the sealant has two sound faces to bond to.
- A backer rod set at the right depth, so the sealant has the right shape and doesn't bond to the bottom of the joint.
- A sealant chosen for the traffic, joint width and exposure, installed below the surface so tires don't pull it out.
Concrete is not asphalt
Asphalt crack filling and sealcoating are maintenance for flexible pavement. Concrete joint sealing is a different job, with different materials and preparation. When you request quotes, make sure the contractor is quoting concrete joint work.
How often to inspect
Walk the pavement at least once a year. Note joints where sealant has hardened, split down the middle, pulled away from an edge, or is missing. Resealing those sections before the base erodes costs far less than replacing cracked panels later.
References
- American Concrete Institute, PRC-330-21: Commercial Concrete Parking Lots and Site Paving Design and Construction Guide. www.concrete.org
- Federal Highway Administration, Technical Advisory T 5040.30: Concrete Pavement Joints. www.fhwa.dot.gov
- Texas Department of Transportation, DMS-6310: Joint Sealants and Fillers. www.txdot.gov